9. Most frame sections need routing out to improve
the bond with the isochanvre. A platform is constructed
on which to assemble the studs
|
|
10. After fabrication the frames are stored in the
compound
|
 |
| |
PRE-ASSEMBLY
|
|
|
| |
 |
|
 |
| |
11. The braced frames are moved from the compound to
the next plots by fork lift with a crane jib attachment
|
|
12. Oversite and scaffolding platforms in place
|
 |
| |
FRAME
ASSEMBLY |
|
|
| |
 |
|
 |
| |
13. Cranes lift the frames over the top of the scaffolding
into a temporary position
|
|
14. Frames are positioned and fixed with holding-down
straps
|
 |
| |
CONSTRUCTING
ROOF |
|
|
| |
 |
|
 |
| |
15. The roof trusses are delivered on site and later
crane handled direct onto the scaffolding round the
Hemp Houses
|
|